Gantt Chart Explained: How to Make, Read and Report It

By Dr. Faheem Afzal Shah, Founder, StatFAS.com · Tool: Gantt Chart Generator

A Gantt chart lays out tasks along a time axis, showing when each starts, how long it lasts and how tasks overlap. In research it is used for project plans, grant timelines, protocol schedules and thesis work. It is a planning visual, not a statistical analysis.

What it shows

Each task is a horizontal bar from its start to its end. Duration = end − start + 1 when counting inclusive periods (such as weeks). Overall span = last end − first start + 1. Dependencies, such as "analysis cannot start before data collection ends", determine the critical sequence that sets the finishing date; tasks outside that sequence have slack.

Original example (illustrative)

TaskStart (week)End (week)Duration (weeks)
Ethics approval144
Participant recruitment3108
Data collection61611
Data analysis17204
Thesis chapter writing19246

The overall span is 24 − 1 + 1 = 24 weeks. Task durations total 33 task-weeks, more than 24, because recruitment overlaps ethics and collection, and writing overlaps analysis. Data collection cannot start before ethics approval ends (week 4), which leaves week 5 as a buffer. Collection, analysis and writing form the sequence that drives the end date, so a delay in collection pushes the whole project unless analysis is compressed.

How to make it in StatFAS

Open the Gantt Chart Generator. Provide task names with start and end values (or start and duration).

Reading and reporting

Include units and the start date, label milestones and note assumptions such as ethics turnaround time. In a proposal, caption the chart: Figure 1. Project timeline in weeks from study start.

Common mistakes and alternatives

Overly optimistic durations, no buffer for approvals, hiding dependencies, mixing weeks and months, and treating the chart as a forecast rather than a plan. Alternatives: milestone tables, kanban boards and network (PERT/critical path) diagrams. See the Project Management Institute's PMBOK Guide for formal scheduling methods.

Conclusion

A Gantt chart makes timing and overlap explicit; keep it realistic and update it as the project changes.

Screenshots to supply (genuine captures only):
1. statfas-gantt-chart-interface.png, alt: "StatFAS Gantt Chart Generator interface"
2. statfas-gantt-chart-example-data.png, alt: "Example data entered in the StatFAS Gantt Chart Generator"
3. statfas-gantt-chart-settings.png, alt: "Gantt Chart Generator settings in StatFAS"
4. statfas-gantt-chart-result.png, alt: "Gantt Chart Generator result generated in StatFAS"

References